|
Quarterly Report
Three months ending 31 December 2005
The commencement of construction at the Cibaliung Gold Project marks an important milestone for Austindo with gold production scheduled to begin in the 4th Quarter of 2006.
Cibaliung Gold Project Indonesia
- Aker Kvaerner were appointed to provide engineering services for the relocation of the Mount Olympus gold processing plant to Indonesia.
- A contract for the dismantling of the Mount Olympus gold processing plant for shipping to Indonesia was awarded.
- A traditional groundbreaking ceremony was held on site to signify the commencement of construction. Preparation of the Box Cut is underway.
- A Project Facility Agreement for the provision of US$26 million project finance signed with ANZ Investment Bank. Drawdown will be effected following execution of security documents and completion of conditions precedent.
Project Generation - Indonesia
- Surface exploration at Pekalongan has identified geochemical anomalies.
- A new tenement area was granted for exploration of gold and its associated minerals, including copper, in the District of Teluk Bintuni, Papua, Indonesia pursuant to the Company’s Strategic Alliance with the Anglo American Group.
Corporate
- The Company issued A$4.0 million of Convertible Notes to clients of Austock Corporate Finance Limited and to Macquarie Bank Limited to satisfy project finance requirements to demonstrate additional capacity to fund contingencies that may arise during construction at the Cibaliung Gold Project.
Expenditure
- Exploration and pre-development expenditure in Indonesia during the quarter totalled A$2,603,000.
CIBALIUNG GOLD PROJECT INDONESIA (85.73% as at 30 June 2005)
The Company’s development focus in Indonesia is the Cibaliung Gold Project which is operated by PT. Cibaliung Sumberdaya, a joint venture company established between the Company and PT. Antam Tbk.
Cibaliung is located in Banten Province near the western tip of the island of Java, 150km south west of Jakarta. In accordance with the terms of the joint venture agreement, the Company’s interest in the Cibaliung Project as at 30 June 2005 stood at 85.73%.
The commencement of work on site was marked by a traditional Ground Breaking Ceremony held during the quarter at the site of the portal to the underground mine. The ceremony was attended by over 200 people including leaders of the local community, government officials and Company representatives.

The Company has completed the acquisition of the gold processing plant located at the Mount Olympus Mine near Paraburdoo in Western Australia which will be relocated to Cibaliung. Aker Kvaerner have been awarded a contract for engineering services associated with the dismantling, transportation, re-erection and plant modifications (including the addition of an elution circuit, detox unit, gold room and backfill plant).
In addition, pre-engineering work for the construction of the project and contract tendering for major site construction elements were advanced during the quarter. A contract for the dismantling of the Mount Olympus gold processing plant for shipping to Indonesia was awarded and work on dismantling of the plant has commenced.
Financing
The Company issued A$4.0 million of Convertible Notes (“Notes”) to Macquarie Bank Limited and clients of Austock Corporate Finance Limited to satisfy project finance requirements to demonstrate additional capacity to fund contingencies that may arise during construction of the mine.
Permitting
The Mining Authorisation and land use permits for the Cibaliung project were finalised during the quarter.
Cibaliung Exploration
Three drill holes (AC-109, AC-110 and AC-111) were completed during the quarter. AC-109 was drilled at West Cibitung but did not intercepted significant structures or mineralisation. AC-110 was drilled in the Central Zone and although low grade, has confirmed the structural zones with few quartz veins at 186.40 206.10. AC-111 was drilled at Ilalang where shear structures were intercepted, coinciding with previously identified IP-resistivity anomalies, however this structure is not mineralised.
Infill ground magnetics was completed and the interpretation was updated. This work greatly aids structural interpretation and will be used to plan the next phase of drill testing targets in close proximity to the known ore shoots. Further drilling is proposed later in 2006.
Expenditure
Expenditure in relation to the development of the Cibaliung Gold Project totalled A$2,377,000.
Expenditure in relation to Cibaliung Exploration totalled A$207,000.
PROJECT GENERATION INDONESIA
Total Expenditure on exploration and evaluation (excluding Cibaliung) in respect of new project generation in Indonesia totalled A$19,000 during the quarter.
Pekalongan, Central Java
An extensive program of stream sediment sampling has been completed at the Pekalongan Gold Project, located in Central Java, resulting in several geochemical anomalies being identified.

At the Kuning prospect, quartz veins and veinlets were identified in several zones trending northwest-southeast, and enveloped by smectite-illite-kaolinite alteration. The quartz veins/ veinlets are millimetres to centimetres in thickness, characterized by fine- to medium-grained quartz with crustiform-colloform banding textures, which are indicative of potential epithermal gold silver mineralisation. Rock geochemistry ranges from <0.1 to 1.75 g/t gold with anomalous arsenic and antimony (5 to 230 g/t and 1 to 28 g/t respectively).
At the Mudal prospect, quartz veinlet zones and stockwork, hosted by illite-smectite-kaolinite altered rocks were identified in close proximity with silica sinter outcrops. Although, the gold grades are low, the arsenic and antimony are elevated (2 to 81 g/t and 1 to 18 g/t respectively) indicating the possibility of a shallow level epithermal system.
Detailed mapping is now being undertaken in each of the prospect areas to assess possible drilling targets.
Papua
A new tenement area was been granted during the quarter for exploration of gold and its associated minerals, including copper, in the District of Teluk Bintuni, Papua, Indonesia pursuant to the Company’s Strategic Alliance with PT Minorco Services Indonesia of the Anglo American Group.
The new tenement area, known as the Aisasjur Prospect, has been granted under a Kuasa Pertambangan (“KP”) which is held by PT Alam Papua Nusantara pursuant to a strategic alliance to explore for large porphyry copper gold deposits. Together with Anglo, Austindo believes that the province of Papua is highly prospective for the discovery of major copper-gold deposits.
The KP covers an area of 9,486 hectares and has been granted for an initial three year period.

Geologically, the Aisasjur Prospect area lies within one of the Indonesia’s young Tertiary volcano- plutonic arcs which are prospective for both porphyry copper-gold and epithermal gold mineralisation styles.
Previous exploration in the area, including drilling, carried out in the 1990’s returned encouraging results and confirmed the presence of significant gold mineralisation.
In accordance with the terms of the strategic alliance, Anglo will sole fund exploration activities at Aisasjur which are scheduled to commence in the near future.
Ian Price
Managing Director & CEO
27 January 2006
The information in this report that relates to Exploration Results is based on information compiled by Mr Sukmandaru Prihatmoko, who is a Member of the Australasian Institute of Mining and Metallurgy.
Mr Prihatmoko is a full-time employee of PT. Indonusa Mining Services, a wholly owned subsidiary of the Company.
He has sufficient experience which is relevant to the style of mineralization and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Prihatmoko consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
ABOUT AUSTINDO RESOURCES CORPORATION NL (ARX)
Formed in 1983, Austindo Resources Corporation NL is an Australian listed gold company focussed on developing projects in Indonesia. The company’s key project is Cibaliung, a high-grade epithermal gold/silver vein system located southwest of Jakarta in Banten Province, western Java. Production at Cibaliung is expected to begin in the 4th quarter of 2006, with an annual production rate of 70,000 oz (gold equivalent) at an average life of mine cash operating costs of approximately US$200 per ounce.
Two key strategic alliances in Indonesia are taking Austindo closer to achieving its growth objective. In association with Anglo American Group, the company is exploring for large porphyry copper/gold deposits in Papua, and also has an interest with PT Sumber Mineral Nusantara in the Pekalongan tenement in Central Java, an area prospective for low sulphidation epithermal gold/silver deposits similar to the Cibaliung project.
Download 31 December, 2005 Quarterly Report (180K)
In order to read this file it is necessary to have the Adobe Acrobat Reader installed on your computer. To download it click on the "Get Acrobat Reader" icon below.

Rule 5.3
Appendix 5B
Mining exploration entity quarterly report
Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001.
Name of entity
|
AUSTINDO RESOURCES CORPORATION N.L.
|
ABN
|
|
Quarter ended ("current quarter")
|
|
48 002 678 640
|
|
31 December 2005
|
Consolidated statement of cash flows
|
Current quarter
$A'000
|
Year to date (.12.months)
$A'000
|
Cash flows related to operating activities
|
|
Including Alexander Resources Ltd March quarter (Note 1)
|
Excluding Alexander Resources Ltd March quarter (Note 1)
|
1.1
|
Receipts from product sales and related debtors
|
-
|
-
|
-
|
1.2
|
Payments for
(a) exploration and evaluation
(b) development (Note 2)
(c) production
(d) administration
|
(226)
(2,377)
-
(276)
|
(2,509)
(6,998)
-
(1,440)
|
(2,468)
(6,998)
-
(1,337)
|
1.3
|
Dividends received
|
-
|
-
|
-
|
1.4
|
Interest and other items of a similar nature received
|
153
|
349
|
346
|
1.5
|
Interest and other costs of finance paid
|
-
|
(109)
|
(109)
|
1.6
|
Income taxes paid
|
-
|
-
|
-
|
1.7
|
Other (provide details if material)
|
-
|
-
|
-
|
|
Net Operating Cash Flows
|
(2,726)
|
(10,707)
|
(10,566)
|
|
Cash flows related to investing activities
|
|
|
|
1.8
|
Payment for purchases of:
(a)prospects
(b)equity investments
(c) other fixed assets
|
-
-
(259)
|
-
-
(484)
|
-
-
(457)
|
1.9
|
Proceeds from sale of:
(a)Alexander Resources Ltd rights
(b)equity investments
(c)other fixed assets
|
406
-
-
|
406
-
-
|
406
-
-
|
1.10
|
Loans to other entities
|
-
|
-
|
-
|
1.11
|
Loans repaid by other entities
|
-
|
55
|
172
|
1.12
|
Other: Decrease in cash with deconsolidation of Alexander Resources Ltd
|
-
|
(2,659)
|
-
|
|
Net investing cash flows
|
147
|
(2,682)
|
121
|
1.13
|
Total operating and investing cash flows (carried forward)
|
(2,579)
|
(13,389)
|
(10,445)
|
Notes: 1. During the year with Alexander Resources Limited (AXD) raising additional capital, Austindo's interests in AXD fell below 50%. Subsequent to this percentage reduction in shareholding Austindo's Directors believed that Austindo no longer had control over AXD. Consequently, Austindo has ceased to account for AXD as a subsidiary and therefore does not include subsequent AXD cashflows in Austindo's consolidated cashflow statement. The consolidated nine month cashflow's including AXD column incorporates the AXD cashflows prior to AXD ceasing to be deemed a subsidiary.
2. Development and project implementation expenditure in relation to the Cibaliung Joint Venture in Banten Province.
|
Current quarter
$A'000
|
Year to date (.12 months)
$A'000
|
|
|
Including Alexander Resources Ltd March quarter
|
Excluding Alexander Resources Ltd March quarter
|
1.13
|
Total operating and investing cash flows (brought forward)
|
(2,579)
|
(13,389)
|
(10,445)
|
|
Cash flows related to financing activities
|
-
|
|
|
1.14
|
Proceeds from issues of shares, options, etc. (net of costs)
|
-
|
19,677
|
18,271
|
1.15
|
Proceeds from sale of forfeited shares
|
-
|
-
|
-
|
1.16
|
Proceeds from borrowings - Convertible Notes |
4,000 |
4,000 |
4,000 |
1.17
|
Repayment of borrowings
|
-
|
(900)
|
(900)
|
1.18
|
Dividends paid
|
-
|
-
|
-
|
1.19
|
Other (Dec Qtr - Convertible Notes fee $160k) |
(160) |
(233)
|
(233)
|
|
Net financing cash flows
|
3,840
|
22,544
|
21,138
|
|
Net increase (decrease) in cash held
|
1,261
|
9,155
|
10,693
|
1.20
|
Cash at beginning of quarter/year to date
|
12,146
|
4,259
|
2,721
|
1.21
|
Exchange rate adjustments to item 1.20
|
24
|
17
|
17
|
1.22
|
Cash at end of quarter
|
13,431
|
13,431
|
13,431
|
Payments to directors of the entity and associates of the directors
Payments to related entities of the entity and associates of the related entities
|
Current quarter
$A'000
|
1.23
|
Aggregate amount of payments to the parties included in item 1.2
|
101
|
1.24
|
Aggregate amount of loans to the parties included in item 1.10
|
-
|
1.25
|
Explanation necessary for an understanding of the transactions
|
|
Represents Managing Director & CEO Salary, Non-Executive Directors’ Fees, and superannuation payments on directors’ fees. |
Non-cash financing and investing activities
2.1
|
Details of financing and investing transactions which have had a material effect on consolidated assets and liabilities but did not involve cash flows
|
|
NIL
|
2.2
|
Details of outlays made by other entities to establish or increase their share in projects in which the reporting entity has an interest
|
|
NIL
|
Financing facilities available
Add notes as necessary for an understanding of the position.
|
|
Amount available
$A'000
|
Amount used
$A'000
|
3.1
|
Loan facilities
|
35,116 |
-
|
3.2
|
Credit standby arrangements
|
-
|
-
|
Estimated cash outflows for next quarter
|
|
$A'000
|
4.1
|
Exploration and evaluation
|
467 |
4.2
|
Development (Note 3) |
12,664
|
|
Total
|
13,131 |
Note 3: Assumes draw down of the ANZ Project Loan in the first quarter of 2006.
Reconciliation of cash
Reconciliation of cash at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts is as follows.
|
Current quarter
$A'000
|
Previous quarter
$A'000
|
5.1
|
Cash on hand and at bank
|
7,999
|
3,326
|
5.2
|
Deposits at call
|
5,432
|
8,820
|
5.3
|
Bank overdraft
|
-
|
-
|
5.4
|
Other (provide details)
|
-
|
-
|
|
Total: cash at end of quarter (item 1.22)
|
13,431 |
12,146
|
Changes in interests in mining tenements
|
|
Tenement reference
|
Nature of interest
(note (2))
|
Interest at beginning of quarter
|
Interest at end of quarter
|
6.1
|
Interests in mining tenements relinquished, reduced or lapsed
|
|
-
|
-
|
-
|
6.2
|
Interests in mining tenements acquired or increased
|
Aisasjur Project KP (held by PT Alam Papua Nusantara) |
Strategic Alliance with the Anglo American Group |
0.0%
|
20.0%
|
Issued and quoted securities at end of current quarter
Description includes rate of interest and any redemption or conversion rights together with prices and dates.
|
Total number
|
Number quoted
|
Issue price per security (see note 3) (cents)
|
Amount paid up per security (see note 3) (cents)
|
7.1
|
Preference +securities (description)
|
-
|
-
|
-
|
-
|
7.2
|
Changes during quarter
(a) Increases through issues
(b) Decreases through returns of capital, buy-backs, redemptions
|
-
-
|
-
-
|
-
-
|
-
-
|
7.3
|
+Ordinary securities
|
1,082,738,890
|
1,082,738,890
|
|
|
7.4
|
Changes during quarter
(a) Increases through issues
(b) Decreases through returns of capital, buy-backs
|
- |
- |
- |
- |
7.5
|
+Convertible debt securities (description)
|
66,666,667* |
Nil |
6 |
6 |
7.6
|
Changes during quarter
(a) Increases through issues
(b) Decreases through securities matured, converted
|
66,666,667*
- |
66,666,667*
- |
6
- |
6
- |
7.7
|
Options (description and conversion factor)
|
6,000,000
3,000,000
4,000,000
2,000,000
14,000,000
each to subscribe
for one ordinary
share in the capital
of the Company
|
-
-
-
-
|
Exercise price
7
7
7
7
7 |
Expiry date
22/05/06
22/10/07
26/05/08
10/12/09
31/07/10 |
7.8
|
Issued during quarter
|
14,000,000 |
-
|
7 |
31/07/10 |
7.9
|
Exercised during quarter
|
-
|
-
|
-
|
-
|
7.10
|
Expired during quarter
|
-
|
-
|
-
|
-
|
7.11
|
Debentures
(totals only)
|
-
|
-
|
|
|
7.12
|
Unsecured notes (totals only)
|
-
|
-
|
|
|
*On 23 November 2005 the Company issued Convertible Notes for $4.0M which are convertible into ordinary fully paid shares at any time at a price of 6 cents per share.
Compliance statement
- This statement has been prepared under accounting policies which comply with accounting standards as defined in the Corporations Law or other standards acceptable to ASX (see note 4).
- This statement does give a true and fair view of the matters disclosed.
Sign here: Date: 31 January 2006
(Company secretary)
Print name: Andrew J Cooke
Notes
- The quarterly report provides a basis for informing the market how the entity's activities have been financed for the past quarter and the effect on its cash position. An entity wanting to disclose additional information is encouraged to do so, in a note or notes attached to this report.
- The "Nature of interest" (items 6.1 and 6.2) includes options in respect of interests in mining tenements acquired, exercised or lapsed during the reporting period. If the entity is involved in a joint venture agreement and there are conditions precedent which will change its percentage interest in a mining tenement, it should disclose the change of percentage interest and conditions precedent in the list required for items 6.1 and 6.2.
- Issued and quoted securities The issue price and amount paid up is not required in items 7.1 and 7.3 for fully paid securities.
- The definitions in, and provisions of, AASB 1022: Accounting for Extractive Industries and AASB 1026: Statement of Cash Flows apply to this report.
- Accounting Standards ASX will accept, for example, the use of International Accounting Standards for foreign entities. If the standards used do not address a topic, the Australian standard on that topic (if any) must be complied with.
|